Lost 3 hours on a Tuesday pour because the total station wouldn't hold a fix
Last Tuesday we had a 60 yard slab pour scheduled for 6am at a job down in Mesa and the whole thing fell apart before the first truck even hit the gate. Our total station kept dropping its fix every 10 minutes, so my layout guy would set a point, climb down, and it would be off by half an inch by the time he got there. We checked the tripod, swapped batteries, re-leveled twice, and still nothing held. Turns out a new cell tower had gone up two blocks over a couple weeks back and the radio channel we were using was getting hammered by interference, which nobody thought to check because the gear worked fine on a job a mile away. We finally switched channels around 8:30, but by then the pump was sitting there burning idle time and the flatwork crew was standing around on their phones. I got the interference report from the dealer after lunch and it basically said what we already figured out, an expensive way to learn a 15 minute lesson. If you're running a robotic setup in a spot with new development nearby, have you had any luck figuring out a clean channel before the pour starts, or do you just eat the lost time?